Work Completed by Town
River Point Parcel Secured and barricaded two Town-owned buildings.
Stapleford Dr. Drainage and roadway repairs.
101 Woods Rd. Test pit waste water lead.
Town Library Repair collapsed storm drain pipe in the parking lot.
Fundy Rd. Drainage improvements, catch basin, ditch and pipe work.
Northbrook Dr. Sink hole repair, catch basin modifications.
82 Blackstrap Rd. Sink hole repair.
Edgewater St. Catch basin repair.
Rt.100 Shoulder washout repair, slope stabilization.
Hillside Ave. Road shoulder repair and ditching.
Country Ln. Repair catch basin and driveway aprons.
334 Falmouth Rd. Replace failing driveway culvert.
Sunny Field Rd. Replace driveway culverts and repave aprons.
Hunters Way Ditching, replace cross culverts and driveway culverts.
Longwoods Rd. Correct driveway slope issues by adding gravel.
11 Leighton Road Installed new catch basin.
Squidere Lane Pavement preservation.
42 Winn Road Roadway repair.
399 Falmouth Rd. Catch basin repair.
Woodville Road Railroad crossing replacement.
Johnson Road Pavement preservation.
Field Road Pavement repair.
31 Brook Road Road failure repair.
Mountain Road Roadside ditching.
Blackstrap Road Shoulder repair/replacement.
Falmouth Road Replaced gravel driveway aprons as part of repaving project.
Contracted Work
Roberts St. Catch basins and piping, easement acquisition.
Rt. # 1 Repair of emergency road/pipe failure. Pipe inlet/outlet repair.
Waites Landing Pipe inlet/outlet repair, slope stabilization.
Falmouth Rd. Repair catch basins and piping.
Longwoods Rd. Reconstruction, pavement overlay, shoulder rebuild.
Brook Road Completed 80% of roadway reconstruction (between Leighton Road and Blackstrap Road).
Falmouth Road Resurfaced from Woodville Road to Leighton Road
Stapleford Dr. Paved the last 150’ of road, plus the cul-de-sac.
Northbrook Dr. Paved section of road where road was in poor condition.
Route 100 Installed pipe liner within existing storm drain pipe under Rte. 100.
Bucknam Road Replaced failing catch basin.
|